project management assignment 1624497 2
This exercise begins with a list of tasks for a wedding project. Working in Microsoft Project, you will create the task list, including summary tasks and their sub-tasks, create links between tasks and their predecessors, add resources, and make changes to the original plan.
A. Enter the following tasks, including the specified duration, specified predecessors, and specified resources. Tasks that are bolded are summary tasks and the indented tasks are sub-tasks. Task List

I put the task list as an attachment
B. Enter the following list of resources into the same Microsoft Project file that you entered the above task list. Resource List

I put the Recource list as an attachment
C. Change the Project from being scheduled from a Start date, to being scheduled from a Finish Date. The Finish Date is the date of the wedding, June 12th, 2016.
D. Change the constraints on the following Tasks:
Task Constraint
Update list of Guests Attending Finish no later than June 10, 2016
Final Fitting Finish no later than June 6, 2016
Schedule Rehearsal Dinner Must start on June 10, 2016
Apply for Wedding License Finish no later than June 10, 2016